Chicago Upstream Network Maintenance
Scheduled Maintenance Report for BitLaunch
Completed
The scheduled maintenance has been completed.
Posted Feb 17, 2024 - 17:00 UTC
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 17, 2024 - 13:00 UTC
Scheduled
Our upstream provider is performing network maintenance:

Our network engineers will be upgrading the top-of-rack core switch and re-working some of the network topologies for a more robust and stable overall network in the server cabinet.

Though the outage is not expected to last more than 30-45 minutes, the work window will be longer as our team will test and ensure connectivity is stable before completing the maintenance.
Posted Feb 13, 2024 - 16:02 UTC
This scheduled maintenance affected: BL Networks (CHI1).